Operators in Russia are preparing to complete a final testing programme at the Leningrad 2-2 nuclear power plant ahead of commercial operation, state nuclear operator Rosenergoatom said.
Rosenergoatom said testing will now continue uninterrupted for 15 days at operating levels of 100% of Leningrad 2-2’s design output.
The company said commercial operation is expected in the coming months, subject to regulatory approval.