Finland utility Teollisuuden Voima Oyj (TVO) said on 2 July it had received “interim information” about a revised schedule for commissioning of the delayed Olkiluoto-3 EPR plant from plant supplier Areva-Siemens.
The company said work on a revised schedule for the 1,600-MW Generation III plant is estimated to be completed in August 2020.
In December 2019 TVO said electricity production at Olkiluoto-3 was scheduled for March 2021, eight months later than the previous target of July 2020.
TVO said a new management team at Areva is preparing a financial solution to complete the project according to the revised schedule.
…