Olkiluoto-3 / TVO Waiting For Revised Commissioning Schedule From Areva-Siemens

Source:

Archived news summary. This item reflects its original publication date. Follow the source link below for the publisher’s full article.

Finland utility Teollisuuden Voima Oyj (TVO) said on 2 July it had received “interim information” about a revised schedule for commissioning of the delayed Olkiluoto-3 EPR plant from plant supplier Areva-Siemens.

The company said work on a revised schedule for the 1,600-MW Generation III plant is estimated to be completed in August 2020.

In December 2019 TVO said electricity production at Olkiluoto-3 was scheduled for March 2021, eight months later than the previous target of July 2020.

TVO said a new management team at Areva is preparing a financial solution to complete the project according to the revised schedule.
…