Building a first of a kind nuclear reactor comes with “known unknowns”

TelegraphOperatorNote to readers: This blog post is the first in an occasional, and irregular, series of news briefs about developments in the nuclear energy field. 

Tennessee

The Tennessean newspaper has a superb roundup on the construction of TVA’s Watts Bar 2 nuclear plant. The utility expects the plant to be completed by the end of 2015. Work on the plant was restarted in 2007 after construction was mothballed in 1985.

The report includes video, charts, history of the plant, and how it will fit in TVA’s energy generation mix.

Georgia & South Carolina

Platts has a roundup on the status of construction of two new Westinghouse AP1000 reactors in Georgia and two more in South Carolina. Meeting tight schedules depends on the ability of contractors building the plant to perform. Rate regulatory agencies in both states are closely watching construction progress for signs of cost over runs.

Finland

NucNet reports that Areva said construction of the Olkiluoto-3 nuclear reactor in Finland will be completed in mid-2016 with commissioning starting at the same time and commercial operation now scheduled for 2018, putting the reactor about nine years behind its original schedule. The latest round of delays have to do with Finnish nuclear regulators approval of a digital instrumental and controls system for the plant. The go ahead was given in April 2014 after four years of review of the first-of-a-kind system in Finland.

China

In China NucNet reports the reactor pressure vessel has been lifted into position at the Sanmen-2 AP1000 reactor, marking the start of the installation phase of the unit, project.

The 280-tonne RPV is China’s first indigenously produced AP1000 reactor pressure vessel. CNNC said it passed all required inspections before being shipped to the construction site on 6 August 2014. The RPV was manufactured by China First Heavy Industries (CFHI) under the supervision of reactor vendor Westinghouse.

South Korea

World Nuclear News reports that South Korea plans to build a 150 MW sodium-coolled demonstration nuclear reactor which would begin operation in 2028. The design will be based on the EBR-II prototype developed by Argonne National Laboratory. A working unit was constructed at the lab’s field station in Idaho, but it was shut down in 1994.

# # #


…