Microreactors / Fuel Fabrication Begins For Marvel With Plant Scheduled To Be Online In 2027

Source:

Archived news summary. This item reflects its original publication date. Follow the source link below for the publisher’s full article.

Fuel for the Marvel microreactor, which Idaho National Laboratory plans to host at its transient reactor test (Treat) facility, is now being fabricated by Triga International, with the first fuel delivery expected in spring 2025, the US Department of Energy announced.

Marvel operation was expected “by the end of 2024” as recently as May 2023, but that timeline had shifted by October, when the DOE said the plant “is expected to be completed in early 2025.”

Now, according to the DOE’s latest announcement, fuel loading for Marvel is anticipated in 2026, with the microreactor expected to be on line by 2027.

…