Layoffs Announced as TVA Renegotiates Bechtel’s Contract for Watts Bar Reactor Completion

Source:

Archived news summary. This item reflects its original publication date. Follow the source link below for the publisher’s full article.

Some 800 workers will lose their jobs at the Tennessee Valley Authority’s Watts Bar 2 project under a renegotiated contract with primary contractor Bechtel Power Corp.

TVA has announced it will take over more of the management responsibilities for completing the reactor. In a statement, TVA vice president Mike Skaggs said, "As we announced this past summer, the pace of construction at Watts Bar unit 2 has been slower than originally planned for the aggressive five-year project … Therefore, TVA has been evaluating the best path forward to efficiently complete the project with a primary focus on safety, quality and cost. The company is taking a deliberate approach in the review and development of the overall construction and licensing schedule."

Bechtel was awarded the $1 billion contract to help finish the partially completed unit in 2007. Services within the contract included engineering, procurement and construction, but the Chattanoogan newspaper reported TVA will now take a more active role in managing the project and will more clearly define each entity’s responsibilities.

As a result, TVA said, 600 craft workers and 200 support staff members will no longer work on the project. Most are employed by Bechtel or Day & Zimmerman.