Work has begun on the refurbishment of the Darlington-3 nuclear power plant in Canada, with the project, Ontario Power Generation (OPG) announced.

Unit 3 is the second of four Candu units at the site to undergo refurbishment in a 10-year project that will enable the station to continue operations until 2055.

The first major work at Darlington-3, defuelling, involves the remote-controlled removal of 6,240 fuel bundles from the reactor over the course of 90 days.

OPG said workers will place these bundles inside water-filled fuel bays for up to 10 years of safe storage. Once the bundles have been removed, the team will drain heavy water from the unit’s reactor systems.
…