Nuclear Street.

← News archive

Russia / Construction Of Concrete Foundation Pit Complete For New Leningrad Nuclear Plant

Source:

Archived news summary. This item reflects its original publication date. Follow the source link below for the publisher’s full article.

Workers have completed the construction of the concrete foundation pit for Unit 8 at Russia’s Leningrad nuclear power station.

First nuclear safety-related concrete is scheduled to be poured for the VVER-1200 plant, known both as Leningrad-8 and Leningrad 2-4, next year.

Rosenergoatom, the nuclear power plant operating division of Russian state nuclear corporation Rosatom, said construction of the pit took about two months and was completed two-and-a-half months ahead of schedule.

The work was carried out by Titan-2, the general contractor for the construction of new power units at Leningrad, 70 km to the west of the city centre of Saint Petersburg on the Gulf of Finland.

…


Questions about this archived item? Contact Nuclear Street.