Vogtle / Georgia Power Likely To Revise Schedule For Hot Testing And Fuel Load At Unit 3

Source:

Archived news summary. This item reflects its original publication date. Follow the source link below for the publisher’s full article.

Georgia Power is likely to adjust the dates for the start of hot functional testing and fuel load for the Vogtle-3 nuclear power plant under construction in the US, but still expects to achieve the November 2021 and 2022 regulatory-approved in-service dates for Units 3 and 4 respectively.

Since October 2020, the Vogtle site in the state of Georgia has seen a significant increase in Covid-19 cases, Georgia Power said. This increase, combined with “other productivity challenges”, continues to impact construction production and the pace of testing activity completion, it added.
…