Nuclear Street.

← News archive

GA-EMS Installs Monitoring System At Watts Bar 2

Source:

Archived news summary. This item reflects its original publication date. Follow the source link below for the publisher’s full article.

General Atomics Electromagnetic Systems (GA-EMS) said Tuesday that its radiation monitoring systems had been deployed successfully at the first U.S. nuclear power plant scheduled to go operational since 1996.

The Tennessee Valley Authority, GA-EMS said, selected the company to provide full radiation monitoring systems for the Watts Bar Unit 2 nuclear power plant, which recently achieved first criticality and is undergoing ascension testing. It is expected to be commercially operable – judged when it has been online at full power for 20 days – by the summer of 2016.

GA-EMS designed, manufactured and delivered full plant radiation monitoring systems to meet a variety of safety requirements, including area and process monitors and control room indicators. The monitoring systems comply with 10CFR50 Appendix B, NQA-1 and Regulatory Guide 1.97.

With the plant undergoing a series of ascension tests, “we now look forward to working with TVA … for decades to come,” said GA-EMS President Scott Forney.

GA-EMS, based in San Diego, Ca., announced in February it had received multiple contracts to deliver radiation monitoring systems to support U.S. nuclear power plants. Nuclear Regulatory Commission Order EA-13-109 mandated installation of radiation monitors and hardened containment vent systems in boiling water reactors (BWRs) with Mark I and Mark II containment designs as part of their post-Fukushima Daiichi safety standard upgrades.

As of February, there were 27 BWRs in the United States that required the modification and GA-EMS had received orders from 18 of those plants. The company has also been working with international plant operators to evaluate radiation monitoring requirements for foreign facilities.


Questions about this archived item? Contact Nuclear Street.