AREVA Launches BEATRICE Testing System; Hits Milestone At Olkiluoto 3

Source:

Archived news summary. This item reflects its original publication date. Follow the source link below for the publisher’s full article.

French nuclear power giant AREVA has launched at its Creusot site in France a new testing system that reproduces on a smaller scale all the components of the reactor coolant system of an EPR-type nuclear reactor.

Known as BEATRICE (Boucle pour l'Etude et l'Analyse du TRansport de produIts de Corrosion dans l'Eau: loop for studying and analyzing the transportation of corrosion products in water), the system recreates the real-life properties of a reactor in terms of temperature, pressure, fluid speed and chemistry in order to observe the behavior of the main components: fuel, steam generators, reactor vessel and piping. The heat produced by the nuclear reaction is simulated by powerful electric heating elements.

AREVA has developed this testing system in order to offer utilities an innovative and reliable solution for the optimization of reactor control, notably to reduce the level of corrosion products forming and circulating within the reactor coolant system that have become radioactive due to contact with the reactor core.

The BEATRICE project is part of AREVA’s Safety Alliance program that groups products and services designed to optimize the safety of nuclear facilities.

European and American utilities and research organizations have already expressed an interest in this innovative project, Areva said.

Philippe SAMAMA, senior executive vice president of AREVA’s Reactors and Services Business Group, said the BEATRICE system is unique in the world and required more than five years of work, to develop.

On Thursday, Areva said I had delivered I&C operational cabinets to Olkiluoto 3 in Finland, calling it a major milestone in the plant’s systems testing phase. The I&C system is used to monitor and control the nuclear power plant and is a key component in reactor operations.

“As a next step, the focus is on the completion of the overall I&C testing campaign on the remaining I&C safety equipment and their delivery to Olkiluoto 3 site during the coming winter,” Areva said.

OL3 Project Director Jean-Pierre Mouroux said the installation would enable the plant’s systems commissioning to begin in the first quarter of 2016. He thanked Finnish, German and French OL3 teams for working to see the project through.

"Now we have in Olkiluoto all the main elements to complete the construction. The main focus now is at the site works to keep the scheduled targets, " said Senior Vice President Jouni Silvennoinen, responsible for the OL3 Project at TVO.